Introduction

This is the fifth step of the analysis at local and municipal level.

Figure: The steps to calculate the costs of heat supply to district heating are highlighted in the Toolchain above

To Top

Estimation of costs for the transport of excess heat to district heating areas

In order to estimate the costs of transporting excess heat from potential sources outside of district heating areas to potential district heating areas the CM - Excess heat transport potential can be used. The module yields levelized costs of excess heat transported to the district heating grid [EUR/MWh]. This can further be used in the next step of calculating heat supply costs in district heating.

To Top

Development of future heat load profiles

Renovation of buildings leads to reductions in energy demand for space heating. This also affects the load profiles of heat demand in the district heating systems: the peak demands in winter decrease and the full load hours increase due to higher shares of hot water generation on the overall heat demand. With the CM - Heat load profiles future heat load profiles can be developed according to different heat-saving levels. This can be done based on load profiles provided in the Hotmaps database (default profiles for all NUTS2 regions in Europe) or based on own profiles uploaded into the toolbox. The resulting load profiles are then used in the next step, the calculation of costs and emission of heat supply in district heating with the dispatch module.

To Top

Calculation of costs and emissions of heat supply in district heating

The costs and emissions of heat supply in district heating system depend on the interaction of the different installed supply capacities. Hereby the least-cost combination of capacities and their operation over time is of interest. In order to analyse the so-called hourly dispatch of different supply technology combinations and the effect on the overall costs and emissions of heat supply in district heating the CM - District heating supply dispatch can be used. With the module several scenarios with the following input data combinations can be calculated in order to derive costs and benefits:

  • Combinations of different technologies in supply portfolios:
    • Excess heat from industry (with or without heat pump)
    • Waste incineration
    • High-efficiency co-generation
    • Solar thermal
    • Geothermal
    • Biomass
    • Heat pumps with different heat sources as e.g.
      • wastewater treatment plants
      • river water
      • excess heat from data centers
  • Prices scenarios:
    • for prices of different energy carriers
    • for prices CO2 emissions

The calculations can be used to identify beneficial supply portfolios in the different representative cities/areas and their sensitivity to important influencing parameters like energy carrier and CO2 prices or interest rate and depreciation time.

The outcomes of this step are the heat supply costs to the district heating system [EUR/MWh] in each of the representative cities/areas and the related CO2 emissions [kt/yr]. These results will then be used in the overall Scenario Assessment in Step 6.

The following figure shows the overall approach.

Figure: Overall approach to the calculation of heat supply to district heating costs

To Top

How to cite

Marcus Hummel, Giulia Conforto, in Hotmaps-Wiki, Guidelines for using the Hotmaps toolbox for analyses at local level (August 2020)

To Top

Authors and reviewers

This page was written by Marcus Hummel and Giulia Conforto (e-think).

☑ This page was reviewed by Mostafa Fallahnejad (EEG - TU Wien).

To Top

License

Copyright © 2016-2020: Marcus Hummel, Giulia Conforto

Creative Commons Attribution 4.0 International License

This work is licensed under a Creative Commons CC BY 4.0 International License.

SPDX-License-Identifier: CC-BY-4.0

License-Text: https://spdx.org/licenses/CC-BY-4.0.html

To Top

Acknowledgement

We would like to convey our deepest appreciation to the Horizon 2020 Hotmaps Project (Grant Agreement number 723677), which provided the funding to carry out the present investigation.

To Top

View in another language:

Bulgarian* Czech* Danish* German* Greek* Spanish* Estonian* Finnish* French* Irish* Croatian* Hungarian* Italian* Lithuanian* Latvian* Maltese* Dutch* Polish* Portuguese (Portugal, Brazil)* Romanian* Slovak* Slovenian* Swedish*

* machine translated